How much of Germany’s electricity do data centres use?

Short answerAbout 4%.

About 4% of Germany’s gross electricity consumption in 2025, or about 21 TWh. Gross consumption is everything the country uses, including what is lost in the grid. The figure is an estimate by the Borderstep Institute, and the German government uses it in its 2026 data-centre strategy. Use has grown: the industry group Bitkom put it at 12 billion kWh (12 TWh) in 2014 and 20 billion kWh in 2024. Germany is Europe’s biggest data-centre market. More than a third of its capacity sits around Frankfurt, which grew up beside the DE-CIX internet exchange and the city’s banks. Germany also has its own rules. Under its Energy Efficiency Act, data centres have had to cover 50% of their electricity with renewable power since 2024, counted over the year, and 100% from 2027. Data centres that open from July 2026 must reuse at least 10% of their energy, for example as heat for buildings. That rises to 20% for those that open from July 2028. Operators must also publish their energy data every year and send it to a federal register. What comes next is uncertain. A study for the economy ministry says German data centres could use about 42 TWh in 2035. The grid regulator plans for about 80 to 115 TWh by 2037, based on projects that companies have reported.

The bigger pictureWorldwide, data centres used about 1.5% of electricity consumption in 2024 (IEA), so Germany’s 4% is well above the world average. Germany’s 21 TWh is about 4.3% of the 485 TWh that all the world’s data centres used in 2025 (Hum’s arithmetic).

Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh. 1 TWh = 1 billion kWh.

Electricity consumption of data centres in Germany (estimates to 2025, forecasts after)
  • 12 TWh 2014, estimated: Bitkom and Borderstep
  • 20 TWh 2024, estimated: Bitkom and Borderstep
  • 21 TWh 2025, estimated: about 4% of gross electricity consumption
  • 42 TWh 2035, forecast: study for the economy ministry
  • 80 TWh 2037, low end: grid regulator’s planning range
  • 115 TWh 2037, high end: grid regulator’s planning range

Unit: TWh a year.

What nobody knows yet
  • Nobody publishes a metered total for all German data centres. The 21 TWh is an estimate.
  • How fast it will grow. Forecasts for the mid-2030s run from about 42 TWh to 115 TWh. The regulator itself says it is doubtful that every reported project will be built.
  • How much of it is AI. The strategy says about 15% of German data centres are used for AI or high-performance computing, but gives no electricity figure for them.
  • Whether the rules will stay as they are. The government’s strategy says it plans to propose changes to the Energy Efficiency Act in 2026.
  • The renewable rule is counted over the year. It does not mean a data centre runs on wind and sun every hour.
Sources (15)

Hum’s sums

  • 21 TWh ÷ 485 TWh = about 4.3% of the world’s data-centre electricity (2025)
Cite this

German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German, giving the Borderstep Institute’s 2025 estimate, as quoted in Hum, “How much of Germany’s electricity do data centres use?”, https://humearth.org/q/germany (quote checked 14 Nov 2026).

Cite the original source first; Hum is where you found it.

What do Wh, kWh and TWh mean?

Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh, and 1 TWh = 1 billion kWh. Hum compares each number with something everyday so you don’t need the units.

Send this answer

Data centres use about 4% of Germany’s electricity: about 21 TWh in 2025. More than a third of the capacity is around Frankfurt.